项目| 文件编号 | 20218 | 工期 | 104天 | 开始时间 | 2018-11-10 | 结束时间 | 2019-02-21 |
| 任务数 | 49K | 整理日期 | 2019/5/18 | 下载次数 | 4065次 | ||
| 下载地址 | 计划文件点击下载(登录后才可以下载) | ||||||
| 项目 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
编号 |
任务名称 |
开始时间 |
结束时间 |
| 1 | Preparation before construction |
2018 November 10 | 2018 November 16 |
| 2 | Insepectinon of trestle foundation |
2018 November 17 | 2018 November 18 |
| 3 | T1 Transfer statinon Installation |
2018 November 17 | 2018 November 24 |
| 4 | No.1 trestle 1~38 shaft installation |
2018 November 17 | 2018 November 28 |
| 5 | No.2 trestle 1 span assenbly |
2018 November 29 | 2018 December 4 |
| 6 | Assembly lf the first span bracket |
2018 December 5 | 2018 December 6 |
| 7 | The third Span Assembly of No.2 trestle |
2018 December 7 | 2018 December 14 |
| 8 | The fourth span assembly of No.2 trestle bridge |
2018 December 7 | 2018 December 14 |
| 9 | Installation of the first span bracket |
2018 December 7 | 2018 December 7 |
| 10 | The first Span installation and correction of the trestle |
2018 December 8 | 2018 December 9 |
| 11 | The second span assembly of No.2 trestle |
2018 December 8 | 2018 December 14 |
| 12 | Assembly of the second span bracket |
2018 December 15 | 2018 December 17 |
| 13 | Assembly of the third span bracket |
2018 December 15 | 2018 December 19 |
| 14 | Assembly of the fourth span bracket |
2018 December 15 | 2018 December 19 |
| 15 | Installation of the second span brackt |
2018 December 18 | 2018 December 19 |
| 16 | The second Span installation and Correction of No.2 trestle |
2018 December 20 | 2018 December 21 |
| 17 | Installation of No.2 trestle 1,2 span pattern steel plate |
2018 December 22 | 2018 December 31 |
| 18 | Installation of the third span bracket |
2018 December 22 | 2018 December 23 |
| 19 | Installatin of the fourth span bracket |
2018 December 24 | 2018 December 25 |
| 20 | The third Span Installation and Correction of No.2 trestle |
2018 December 26 | 2018 December 27 |
| 21 | The fourth Span Installation and Correction of No.2 trestle |
2018 December 28 | 2018 December 29 |
| 22 | The fifth span assembly of No.2 trestle |
2018 December 30 | 2019 January 6 |
| 23 | Installatino of trestle 3 and 4 span steel plate |
2018 December 24 | 2019 January 4 |
| 24 | The sixth span assembly of No.2 trestle |
2018 December 30 | 2019 January 7 |
| 25 | No.1 trestle construction preparation |
2018 December 24 | 2018 December 28 |
| 26 | No.1 trestle installation |
2018 December 28 | 2019 February 8 |
| 27 | The fifth span bracket assembly |
2018 December 24 | 2018 December 30 |
| 28 | The sixth span bracket assembly |
2018 December 26 | 2019 January 3 |
| 29 | Installation of the fifth span bracket |
2018 December 31 | 2019 January 2 |
| 30 | Installation of the sixth span bracket |
2019 January 4 | 2019 January 6 |
| 31 | The fifth Installation and correction of No.2 trestle |
2019 January 7 | 2019 January 8 |
| 32 | The sixth Installation and correction of No.2 trestle |
2019 January 8 | 2019 January 12 |
| 33 | The seventh assembly of No.2 trestle |
2019 January 8 | 2019 January 16 |
| 34 | The eighth span assemly of No.2 trestle |
2019 January 8 | 2019 January 16 |
| 35 | Installation of No.2 trestle 5and6 Pattern Stell Plate |
2019 January 5 | 2019 January 17 |
| 36 | The seventh span bracket assembly |
2018 December 31 | 2019 January 7 |
| 37 | The eighth span bracket assembly |
2019 January 4 | 2019 January 12 |
| 38 | Installation and Correction of the seventh span bracket |
2019 January 13 | 2019 January 15 |
| 39 | Installation and Correction of the eighth span bracket |
2019 January 16 | 2019 January 18 |
| 40 | Installation of steel support stair platform |
2019 January 19 | 2019 January 28 |
| 41 | Installation and Correction of 7th and 8th span No.2 trestle |
2019 January 19 | 2019 January 23 |
| 42 | Installation of 7th and 8th span No.2 trestle |
2019 January 18 | 2019 January 30 |
| 43 | The ninth and tenth of assembly of No.2 trestle |
2019 January 24 | 2019 February 2 |
| 44 | The ninth and tenth span assembly |
2019 January 19 | 2019 January 27 |
| 45 | The ninth and tenth bracket installation |
2019 January 28 | 2019 February 1 |
| 46 | The ninth and tenth installation of No.2 trestle |
2019 February 2 | 2019 February 7 |
| 47 | Installation of ninth and tenth pattern steel plate |
2019 January 31 | 2019 February 10 |
| 48 | 第11跨拼装 |
2019 February 8 | 2019 February 16 |
| 49 | 第11跨花纹钢板安装 |
2019 February 17 | 2019 February 21 |